Warwick Highway Weekly Log Oct. 25 - 31, 2010 Mon. Oct. 25 Crushed dumpsters at transfer station Took dump body off truck # 3 noticing left rear tire oil seal leak - brought to Porter's for repair Organized culvert pipe area including removal of dead trees Checked in with National Grid workers on Gale Rd. who are continuing to put wire on new poles Did preliminary driveway inspection on Hastings Pond Rd. Tues. Oct. 26 Jim on vacation day Tim went to National Grid storm meeting in Leominster Cleaned out basins on Barber Hill Picked up truck # 3 from Porter's Diesel Wed. Oct. 27 Tim went to Sturbridge to Bay State Roads advisory board meeting and received his Master Road Scholar award Put sander body on truck # 3 Continued organizing garage area Thurs. Oct. 28 Began putting gravel on edge of Orange Rd. where we previously paved Fri. Oct. 29 Continued putting gravel on edge of Orange Rd. where we previously paved