Warwick Highway Weekly Log Feb. 4 - 10, 2008 Mon. Feb. 4 * Sanded all dirt roads due to icy conditions * Checked hazardous waste area for leaks finding none * Crushed dumpsters at landfill * Changed cutting edge on truck # 3 plow * Cut down tree that was damaged in accident on Fri. on Hasting Heights Rd. * T & R Custom came to look at loader due to transmission overheating - made temporary repairs until replacement part arrives Tues. Feb. 5 * All personnel came in to sand paved roads at midnight due to light snow that changed to freezing rain and rain - sanded dirt roads at 4 A.M. - re-sanded dirt roads after lunch - went home at 2:45 P.M. * Scraped off slush on main roads * Received call from Shelburne Control that Police Chief is reporting water build up on bridge over Orcutt Brook on Orange Rd. - several water issues were taken care of throughout town * Moved wood chunks that Lewis Tree cut up that rolled into road on Old Winchester Rd. Wed. Feb. 6 * Sanded all dirt roads due to continued rain - re-sanded Old Winchester Rd. and Robbins Rd. due to bus getting stuck * Re-scraped various roads in town to get ice off roads * Went around town with loader getting water areas drained * Met with Jim Toth to go over highway issues * Re-sanded dirt roads after lunch due to continued rain * Called all personnel in for 7 P.M. to be ready for ice, sleet and snow storm Thurs. Feb. 7 * Started sanding paved roads at 12:30 A.M. when heavy rain and thunderstorms switched to heavy sleet - began plowing main roads at 4 A.M. - called in private contractors at 5:45 A.M. - began re-sanding all roads at 7:30 A.M. - began re-plowing paved roads at 12:30 p.m. - went home at 3:30 P.M. Fri. Feb. 8 * All personnel came in at 3 A.M. to sand all roads due to dusting of snow * Repaired truck # 2 plow that had minor damage from storm * Went to Pete's Tire to have truck tire repaired and got other supplies while in Orange * Washed out sanders and greased them * Tightened chain on truck # 2 sander * Scraped off various roads in town with 1-Ton * Made minor wiring repairs to truck # 3 Sat. Feb. 9 * Called in personnel at 3 P.M. to begin sanding paved roads - called in private contractors and began plowing at 8:15 P.M. - began sanding all roads at 12:30 A.M. - went home at 4:15 A.M. on Sun. - 4" heavy, wet snow Sun. Feb. 10 * Called in personnel at 4 P.M. to get plows ready to clean up roads after snow squalls - called in private contractors at 5:15 P.M. and began plowing - began sanding all roads at 9 P.M. - went home at 1 A.M. on Mon. - 1" snow