Warwick Highway Weekly Log June 15 - 21, 2009 Mon. June 15 * Checked hazardous waste area for leaks finding none * Crushed dumpsters at transfer station * Repaired a spring in the road on Chestnut Hill Rd. and lined it with stone to harden up roadway * Checked roads for damage due to heavy rain and made repairs as necessary * Hauled 4 loads of rip rap from Lane Const. Back to hwy. garage stockpile * Installed two new street signs to replace stolen ones * Called Police to report damaged street sign that occurred over the weekend sometime Tues. June 16 * Began milling operation on Orange Rd. - worked until 5 P.M. * Began graveling operations on Gale Rd. to replace gravel lost during ice storm Wed. June 17 * Began paving operations on Orange Rd. - worked until 8 P.M. * Fixed several minor washouts around town with rip rap * Mixed up millings we received from Orange Rd. with gravel * Smoothed out potholes on Old Winchester Rd. * Continued graveling operations on Gale Rd. to replace gravel lost during ice storm Thurs. June 18 * Cleaned out culverts and bleeders on Richmond Rd. Fri. June 29 * Finished cleaning out culverts and bleeders on Richmond Rd. * Put crushed gravel by driveways and mailboxes as needed on Orange Rd. where we paved Wed. * Washed trucks and cleaned them up